This Regulatory Investment Test for Distribution (RIT-D) arises because of the condition of the No.3 transformer, which is one of the three 22/6.6kV transformers at FF, is deteriorating and at risk of failure, which poses both a safety and a reliability risk.
In accordance with Clause 5.17.4 of the NER, the first stage of the RIT-D process is to screen for and determine if a non-network option is credible, or can form a significant part of a potential credible option to address the identified need (i.e. network problem or limitation).
If a credible non-network option is identified then a non-network options report is required to be published for consultation. However if it has been investigated and determined that no non-network option can form a significant part of a potential credible option, then a non-network options notice of determination is required to be published.
Published below is Jemena’s non-network options notice of determination for Fairfield Zone Substation (FF) Transformer No.3 Condition and 4th Bus project.
Fairfield Zone Substation transformer replacement and bus NOD
This document is Jemena’s Fairfield Zone transformer replacement and bus – Draft Project Assessment Report. In accordance with the requirements of the National Electricity Rules this report describes:
All submissions and enquires relating to this draft project assessment report must be lodged with us on or before 06 October 2023.
Published below is Jemena’s updated Final Project Assessment Report (FPAR) for Fairfield Zone Substation transformer replacement and bus which concludes the RIT-D consultation process.
FPAR is prepared under clause 5.17.4(o) of the National Electricity Rules (NER) forms Stage 3 of the Regulatory Investment Test for Distribution (RIT-D) consultation process. It sets out the matters detailed in the Draft Project Assessment Report (DPAR) published on 6 September 2023, and summarises the submissions received on that report.
In accordance with clause 5.17.5 of the NER, within 30 days of the date of publication of this FPAR, any party disputing the conclusion made in this FPAR should give notice of the dispute in writing setting out the grounds for the dispute (the dispute notice) to the AER.
Jemena will proceed to implement the preferred option if there are no dispute notices received before 19 January 2024.
• Fairfield Zone Substation transformer replacement and bus FPAR