Comply with Bushfire Mitigation Regulations on Jemena’s Kalkallo 22kV Feeders

This Regulatory Investment Test for Distribution (RIT-D) arises because the safety and compliance requirement for JEN to comply with bushfire mitigation obligations on its 22kV feeders originating from AusNet Services’ Kalkallo (KLO) zone substation.

 

Non-network options Screening Notice

In accordance with Clause 5.17.4 of the NER, the first stage of the RIT-D process is to screen and determine if a non-network option is, or form a significant part of a potential credible option to address the identified need (i.e. network problem or limitation) on the network.

If a credible non-network option is identified then a non-network options report is required to be published for consultation. However if it has been investigated and determined that no non-network option can form a significant part of a potential credible option, then a non-network options screening notice is required to be published. Published below is Jemena’s non-network options screening notices for Comply with Bushfire Mitigation Regulations on Jemena’s Kalkallo 22kV Feeders project. 

 

Draft Project Assessment Report

This document is Jemena’s Comply with Bushfire Mitigation Regulations at KLO – Draft Project Assessment Report . In accordance with the requirements of the National Electricity Rules this report describes:

  • the identified need in relation to the KLO area network within JEN;
  • the credible options assessed that may address the identified need;
  • the methodologies used to quantify market benefits;
  • the net present value assessment results for the potential credible options assessed; and
  • the technical characteristics of the proposed preferred credible option.

All submissions and enquires relating to this draft project assessment report must be lodged with us on or before 3 September 2021.