Queensland Gas Pipeline

Last updated 24 April 2020

For the next 12 months, Jemena has scheduled maintenance which may result in a flow restriction.

This maintenance plan is current, and we will notify you of any material changes.

Start Date End Date Site Activity Available Capacity (TJ/d)
15 Aug 202020 Aug 2020Banana Compressor StationRoutine Maintenance114.9
22 Aug 202027 Aug 2020Rolleston Compressor StationRoutine Maintenance114.9
22 Aug 202027 Aug 2020Rolleston Compressor StationRoutine Maintenance114.9
2 Nov 20202 Nov 2020Larcom Creek Meter StationRoutine Maintenance145
7 Dec 20207 Dec 2020Rolleston Compressor StationRoutine Maintenance112.2
22 Feb 202124 Feb 2021Rolleston Compressor StationRoutine Maintenance112.2
26 Feb 202128 Feb 2021Banana Compressor StationRoutine Maintenance112.7
8 Feb 202110 Feb 2021Moura Meter StationRoutine Maintenance145

This forecast has been prepared by Jemena’s maintenance planning team, taking into account, current maintenance plans, regulatory requirements, forecast projects, resource availability and impacts of any outages on customers.