Start Date End Date Site Activity Available Capacity (TJ/d)
2 Feb 2021 3 Feb 2021 Rolleston Compressor Station Routine Maintenance 112.2
3 Feb 2021 3 Feb 2021 RCS GEA U2 Installation Routine Maintenance 112.2
4 Feb 2021 4 Feb 2021 RCS GEA U2 Commissioning Routine Maintenance 112.2
9 Feb 2021 10 Feb 2021 Banana Compressor Station Routine Maintenance 112.7
9 Feb 2021 9 Feb 2021 RCS GEA U1 Disconnection Routine Maintenance 112.2
22 Feb 2021 24 Feb 2021 Rolleston Compressor Station Routine Maintenance 112.2
26 Feb 2021 27 Feb 2021 Banana Compressor Station Routine Maintenance 112.7
1 Apr 2021 1 Apr 2021 Rolleston Compressor Station Routine Maintenance 112.7
28 Apr 2021 28 Apr 2021 RCS GEA U1 Installation Routine Maintenance 112.7
29 Apr 2021 29 Apr 2021 RCS GEA U1 Commissioning Routine Maintenance 112.7
3 May 2021 3 May 2021 BCS GEA U1 DEA Function Test Routine Maintenance 114.9
4 May 2021 4 May 2021 BCS GEA U1 Disconnection Routine Maintenance 114.9
1 Jun 2021 1 Jun 2021 Rolleston Meter Station Routine Maintenance 114.3
14 Jul 2021 14 Jul 2021 BCS GEA U1 Installation Routine Maintenance 114.9
15 Jul 2021 15 Jul 2021 BCS GEA U1 Commissioning Routine Maintenance 114.9
1 Aug 2021 1 Aug 2021 Rolleston Meter Station Routine Maintenance 114.3
1 Aug 2021 8 Aug 2021 Banana Compressor Station Routine Maintenance 114.9
15 Aug 2021 18 Aug 2021 Rolleston Compressor Station Routine Maintenance 114.3