Queensland Gas Pipeline

Last updated 25 January 2020

For the next 12 months, Jemena has scheduled maintenance which may result in a flow restriction.

This maintenance plan is current, and we will notify you of any material changes.

Start Date End Date Site Activity Available Capacity (TJ/d)
26 Feb 2020 28 Feb 2020 Rolleston Compressor Station Routine Maintenance 112.2
3 Mar 2020 5 Mar 2020 Banana Compressor Station Routine Maintenance 112.7
15 Aug 2020 20 Aug 2020 Banana Compressor Station Routine Maintenance 114.9
22 Aug 2020 27 Aug 2020 Rolleston Compressor Station Routine Maintenance 114.9

This forecast has been prepared by Jemena’s maintenance planning team, taking into account, current maintenance plans, regulatory requirements, forecast projects, resource availability and impacts of any outages on customers.