Eastern Gas Pipeline

Last updated 30 December 2019

For the next 12 months, Jemena has scheduled maintenance which may result in a flow restriction.

This maintenance plan is current, and we will notify you of any material changes.

Start Date End Date Site Activity Available Capacity (TJ/d)
12 Feb 2020 28 Feb 2020 Longford Compressor Station Routine Maintenance 310
3 Mar 2020 3 Mar 2020 Longford Compressor Station Routine Maintenance 310
4 Mar 2020 5 Mar 2020 Mila Compressor Station Routine Maintenance 291
4 Mar 2020 6 Mar 2020 Horsley Park Scraper Station Routine Maintenance 352
9 Mar 2020 13 Mar 2019 Mila Compressor Station Routine Maintenance 291
18 Mar 2020 20 Mar 2020 Horsley Park Scraper Station Routine Maintenance 352
1 May 2020 31 May 2020 Longford Compressor Station Routine Maintenance 310
5 Jun 2020 15 Jun 2020 Longford Compressor Station Routine Maintenance 330
2 Sep 2020 13 Sep 2020 Longford Compressor Station Routine Maintenance 310
5 Oct 2020 12 Oct 2020 Longford Compressor Station Routine Maintenance 310
15 Oct 2020 20 Oct 2020 Michelago Compressor Station Routine Maintenance 294
25 Nov 2020 29 Nov 2020 East Gippsland Compressor Station Routine Maintenance 305
2 Dec 2020 12 Dec 2020 Longford Compressor Station Routine Maintenance 310

This forecast has been prepared by Jemena’s maintenance planning team, taking into account, current maintenance plans, regulatory requirements, forecast projects, resource availability and impacts of any outages on customers.