Darling Downs Pipeline

Last updated 28 October 2020

For the next 12 months, Jemena has scheduled maintenance which may result in a flow restriction.

This maintenance plan is current, and we will notify you of any material changes.

Start Date End Date Site Activity Available Capacity (TJ/d)
5 Apr 20216 Apr 2021PPL090Routine Maintenance139.6
7 Apr 20218 Apr 2021PPL133Routine Maintenance417
9 Apr 202110 Apr 2021PPL134Routine Maintenance250
9 Oct 202110 Oct 2021PPL090Routine Maintenance139.6
11 Oct 202112 Oct 2021PPL133Routine Maintenance417
13 Oct 202114 Oct 2021PPL134Routine Maintenance250

This forecast has been prepared by Jemena’s maintenance planning team, taking into account, current maintenance plans, regulatory requirements, forecast projects, resource availability and impacts of any outages on customers.