Darling Downs Pipeline

Last updated 24 April 2021

For the next 12 months, Jemena has scheduled maintenance which may result in a flow restriction.

This maintenance plan is current, and we will notify you of any material changes.

Start Date End Date Site Activity Available Capacity (TJ/d)
11 May 2021 12 May 2021 DDP Routine Maintenance 440
1 Jun 2021 1 Jun 2021 SGW Routine Maintenance 0
1 Aug 2021 1 Aug 2021 Talinga Meter Station Routine Maintenance 0
2 Aug 2021 2 Aug 2021 ML1A Routine Maintenance 0
9 Oct 2021 10 Oct 2021 PPL090 Routine Maintenance 139.6
11 Oct 2021 12 Oct 2021 PPL133 Routine Maintenance 417
13 Oct 2021 14 Oct 2021 PPL134 Routine Maintenance 250
1 Feb 2022 1 Feb 2022 Kenya Meter Station (PPL133 Routine Maintenance 0
1 Feb 2022 1 Feb 2022 SGW Routine Maintenance 0
5 Apr 2022 6 Apr 2022 PPL090 Routine Maintenance 139.6
7 Apr 2022 8 Apr 2022 PPL133 Routine Maintenance 417
9 Apr 2022 10 Apr 2022 PPL134 Routine Maintenance 250
1 Aug 2022 1 Aug 2022 Talinga Meter Station Routine Maintenance 0
2 Aug 2022 2 Aug 2022 ML1A Routine Maintenance 0
9 Oct 2022 10 Oct 2022 PPL090 Routine Maintenance 139.6
11 Oct 2022 12 Oct 2022 PPL133 Routine Maintenance 417
13 Oct 2022 14 Oct 2022 PPL134 Routine Maintenance 250

This forecast has been prepared by Jemena’s maintenance planning team, taking into account, current maintenance plans, regulatory requirements, forecast projects, resource availability and impacts of any outages on customers.