Queensland Gas Pipeline

Last updated 24 October 2018

For the next 12 months, Jemena has scheduled maintenance which may result in a flow restriction.

This maintenance plan is current, and we will notify you of any material changes.

Start Date End Date Site Activity Available Capacity (TJ/d)
13 Nov 201814 Nov 2018Banana Compressor StationRoutine Maintenance113
6 Mar 20199 Mar 2019Rolleston Compressor StationRoutine Maintenance110
26 Mar 201929 Mar 2019Banana Compressor StationRoutine Maintenance112
26 Jun 201926 Jun 2019Gladstone City GateRoutine Maintenance136

This forecast has been prepared by Jemena’s maintenance planning team, taking into account, current maintenance plans, regulatory requirements, forecast projects, resource availability and impacts of any outages on customers.