Queensland Gas Pipeline

Last updated 27 April 2019

For the next 12 months, Jemena has scheduled maintenance which may result in a flow restriction.

This maintenance plan is current, and we will notify you of any material changes.

Start Date End Date Site Activity Available Capacity (TJ/d)
26 Jun 201926 Jun 2019Gladstone City GateRoutine Maintenance136
29 Jul 20199 Aug 2019Banana Compressor StationRoutine Maintenance112
12 Aug 201920 Sep 2019Banana Compressor StationRoutine Maintenance139
12 Aug 201920 Sep 2019Rolleston Compressor StationRoutine Maintenance139
3 Sep 20193 Sep 2019Yarwun Offtake StationRoutine Maintenance112
3 Sep 20198 Sep 2019Yarwun Offtake StationRoutine Maintenance110
24 Feb 202025 Feb 2020Rolleston Compressor StationRoutine Maintenance110
26 Feb 202027 Feb 2020Banana Compressor StationRoutine Maintenance110
22 Apr 202026 Apr 2020Rolleston - Compressor Engine ReplacementRoutine Maintenance110

This forecast has been prepared by Jemena’s maintenance planning team, taking into account, current maintenance plans, regulatory requirements, forecast projects, resource availability and impacts of any outages on customers.