Queensland Gas Pipeline

Last updated 22 January 2018

For the period 1 January 2018 to 31 December 2018, Jemena has scheduled maintenance which may result in a flow restriction.

This maintenance plan is current, and we will notify you of any material changes.

Start Date

End Date Site Activity Available Capacity (TJ/d)
16 Jan 16 Jan Banana Compressor Station Install temporary UPS at BCS 112
19 Mar 21 Mar Banana Compressor Station Compressor Unit 5 Semi Annual Maintenance BCS 112
22 Apr 24 Mar Rolleston Compressor Station Compressor Unit 9 Semi-Annual Maintenance RCS 110
1 May 2 May Rolleston Compressor Station and Banana Compressor Station BCS and RCS UPS and Batteries Replacement 111 - 113
20 Aug 25 Aug Banana Compressor Station Compressor Unit 5 Annual maintenance BCS 112
25 Aug 28 Aug Rolleston Compressor Station Compressor Unit 9 Annual maintenance RCS 110
1 Sep 6 Sep Yarwun Offtake Station Water Bath Heater Burner Inspection -YOS 139

This forecast has been prepared by Jemena’s maintenance planning team, taking into account, current maintenance plans, regulatory requirements, forecast projects, resource availability and impacts of any outages on customers.