Queensland Gas Pipeline

Last updated 23 August 2018

For the next 12 months, Jemena has scheduled maintenance which may result in a flow restriction.

This maintenance plan is current, and we will notify you of any material changes.

Start Date End Date Site Activity Available Capacity (TJ/d)
3 Sep 2018 11 Sep 2018 Banana Compressor Station Routine Maintenance 112
3 Sep 2018 11 Sep 2018 Rolleston Compressor Station Routine Maintenance 110
13 Nov 2018 14 Nov 2018 Banana Compressor Station Routine Maintenance 113
6 Mar 2019 9 Mar 2019 Rolleston Compressor Station Routine Maintenance 110
26 Mar 2019 29 Mar 2019 Banana Compressor Station Routine Maintenance 112
26 Jun 2019 26 Jun 2019 Gladstone City Gate Routine Maintenance 136

This forecast has been prepared by Jemena’s maintenance planning team, taking into account, current maintenance plans, regulatory requirements, forecast projects, resource availability and impacts of any outages on customers.