Darling Downs Pipeline

Last updated 22 May 2019

For the next 12 months, Jemena has scheduled maintenance which may result in a flow restriction.

This maintenance plan is current, and we will notify you of any material changes.

Start Date End Date Site Activity Available Capacity (TJ/d)
13 May 201914 May 2019ML1ARoutine MaintenceSouthern Haul: 155 TJ/d Northern Haul: 40 TJ/d Western Haul: 275 - 540 TJ/d Eastern Haul: 200 - 270 TJ/d
12 Aug 201916 Aug 2019DDP134Routine MaintenceSouthern Haul: 155 TJ/d Northern Haul: 40 TJ/d Western Haul: 173 - 540 TJ/d Eastern Haul: 200 - 173 TJ/d
19 Sep 201919 Sep 2019DDP133Routine MaintenceSouthern Haul: 155 TJ/d Northern Haul: 40 TJ/d Western Haul: 275 - 80 TJ/d Eastern Haul: 150 - 270 TJ/d
15 Oct 201915 Oct 2019DDP134Routine MaintenceSouthern Haul: 110 TJ/d Northern Haul: 0 TJ/d Western Haul: 150 - 173 TJ/d Eastern Haul: 150 - 173 TJ/d

This forecast has been prepared by Jemena’s maintenance planning team, taking into account, current maintenance plans, regulatory requirements, forecast projects, resource availability and impacts of any outages on customers.