Darling Downs Pipeline

Last updated 02 August 2018

For the next 12 months, Jemena has scheduled maintenance which may result in a flow restriction.

This maintenance plan is current, and we will notify you of any material changes.

Start Date End Date Site Activity Available Capacity (TJ/d)
15 Aug 2018 15 Aug 2018 DDP Routine Maintenance

Southern Haul: 110 TJ/d

Northern Haul: 0 TJ/d

Western Haul: 275 - 540 TJ/d

Eastern Haul: 200 - 270 TJ/d

15 Oct 2018 15 Oct 2018 DDP Routine Maintenance

Southern Haul: 110 TJ/d

Northern Haul: 0 TJ/d

Western Haul: 80 - 173 TJ/d

Eastern Haul: 80 - 173 TJ/d

16 Apr 2019 16 Apr 2019 DDP Routine Maintenance

Southern Haul: 155 TJ/d

Northern Haul: 40 TJ/d

Western Haul: 275 - 80 TJ/d

Eastern Haul: 80 - 270 TJ/d

18 Apr 2019 18 Apr 2019 DDP Routine Maintenance

Southern Haul: 155 TJ/d

Northern Haul: 40 TJ/d

Western Haul: 173 - 540 TJ/d

Eastern Haul: 200 - 173 TJ/d

19 Apr 2019 19 Apr 2019 DDP Routine Maintenance

Southern Haul: 110 TJ/d

Northern Haul: 0 TJ/d

Western Haul: 275 - 540 TJ/d

Eastern Haul: 200 - 270 TJ/d

This forecast has been prepared by Jemena’s maintenance planning team, taking into account, current maintenance plans, regulatory requirements, forecast projects, resource availability and impacts of any outages on customers.