Click on the links below to obtain further information:
A customer intending to connect a generator to Jemena's network via an inverter with a rating of 10kVA per phase or less can connect using a streamlined connection process. This process can be used for most rooftop solar (photovoltaic) generators. The generator can be commissioned without written approval from Jemena or a signed connection agreement with Jemena however the system owner must nonetheless fully comply with Jemena's technical standards and applicable industry standards and must complete and submit the appropriate forms. The generator owner can then assume automatic approval is granted without Jemena reviewing the application if the installation satisfies these standards.
A feature of solar generating systems is their ability to export energy back into the electricity supply grid. Jemena encourages generation of electricity from renewable sources however it must place certain conditions on the generating systems to ensure that they do not compromise the safety or integrity of the electricity supply grid as a whole.
The connection to the electricity grid must be instigated through an Electricity Retailer of your choice. The following conditions must be met before connection can be made to the Jemena electricity grid.
Requirements for Grid Connected Systems via an Inverter
If all of the above conditions are met then the generator owner can assume they have approval to connect their embedded generator to the low voltage network.
The ongoing connection of the embedded generator to the electricity distribution network is dependent on the generator and associated equipment being maintained such that it continues to comply with the above conditions. Jemena reserves the right to disconnect from the electricity distribution grid any embedded generator at any time if it becomes aware of its non-compliance with the above conditions.
Jemena will not be responsible for any loss incurred by the generator owner resulting from its connection or disconnection to the electricity distribution network.
The 'Solar Connection Form' is a document that must be filled out and signed by the customer and sent to Jemena before the system is connected to the distribution network. This provides important information that Jemena must collect to manage its distribution network. Click here to obtain a copy of the form.
Jemena Victorian Electricity Distribution Network
Effective from 1 January 2006
Victorian Electricity Supply Industry
Abolishment of Supply
Supply Interruptions
Public Lighting
Tariff Strategy Report
Network Tariffs
Excluded Services Charges
Embedded Generation
Connection of Solar or other Small Embedded Generators via an Inverter
Metering Diagrams
Customer Claims
Planning
Reliability Service Level Targets
Contact Demand Reset Policy
New Connections and Tendering Guide